Invicta Building Services were delighted to work with the Royal Borough of Greenwich on the plantroom refurbishment at Cherry Orchard Primary School

The project included the isolation, disconnection, strip out and safe disposal of all existing boiler plant service equipment and pipe work.

The provision and installation of 3 new Hamworthy Stratton mk3 S3-100 wall hung gas fired condensing boilers with a total output of 101kW.

Each was installed with a replacement individual flue system.

Additionally, we installed  a new condensate drainage system to the boilers and flues. We altered the existing gas installations to supply gas services to the new condensing boilers.

Other works included: new primary loop, VT circulation and CT circulation pumps, new air separator for the heating system, 2 new domestic hot water calorifiers, TRV guards on all the TRVs, new pipework arrangement including a two-port valve from the existing heat pump to the new calorifier, new BMS control system housed within a Motor Control Panel.

We validated and enhanced the ASHP controls as required, including a new buffer vessel, and retained all pipework related to the air source heat pumps and primary pipework to the plate heat exchanger.

We completed the replacement of local heat emitters at selected locations throughout the school

We completed additional water heater works in the school kitchen

All works took place during the summer holiday and equipment operational before the school reopened for the new term.